Client:
Mobil Producing Nigeria
Other Partners:
60.0% NNPC
Details:
YA Wellhead Platform
300feet (91meters) water depth
Project Team:
Petromarine (Engineering)
Twin Brothers Marine (Shipyard)
Global Offshore International (EPC Contractor)
Installation:
Louisa, LA USA (onshore)
Yoho Field, Nigeria (offshore)
FIBERBOND® Scope:
Supply of materials
Shop prefabrication
Site installation including FRP welding
Installation of supports, installation of flanges, and commissioning assistance
Systems Selected for FIBERBOND®:
Firewater, firewater deluge, seawater
3,200feet (975meters) of piping, up to 16" (400NB)
ABS-type approved products
200psig (13.8bar) design, 300psig (20.7bar) hydrotest
Highlights:
Part of the 1st EPS (early production system) installed in west Africa
Installed warranty on entire system
Operating since 2002