Home > Application Data > Case Histories > BHP Shenzi TLP

BHP Billiton "Shenzi" TLP

Client: BHP Billiton
Other Partners: Hess (28%); Repsol (28%)

Details:
Largest Modec-Moses design TLP (15,500 ton topsides capacity; 43,500 ton displacement)
Green Canyon 653; 4300ft (1310m) water depth

Project Team:
Samsung Heavy Industries (Hull)

Alliance Engineering (Engineering)
Kiewit Offshore Services (Shipyard)

Installation:
Ingleside, TX (onshore)
Green Canyon 653 (offshore)

FIBERBOND® Scope:
Supply of materials
Shop prefabrication
Site installation including FRP welding
Installation of supports, installation of flanges, and commissioning assistance

Systems Selected for FIBERBOND®:
Seawater, firewater, drains
20,995feet (6,399meters) of piping, up to 16" (400NB)
ABS and USCG type approved products
Up to 200psig (13.8bar) design, up to 300psig (20.7bar) hydrotest

Highlights:
Largest ever Modec-Moses design TLP
Installed warranty on entire system
Scheduled for operation in 2009